In 4 years, 28 new hydropower plants with a total capacity of over 400 MW have been built, - President Japarov
The President noted that many of the oldest plants, such as the Toktogul HPP, built in the 1950s, 60s, and 70s, had not undergone repairs for decades and had operated for more than 50 years without interruption.
“When we came to power, the condition of these facilities was critical. Over four years, a large-scale modernization was carried out: four units at the Toktogul HPP were updated, which allowed for an increase in capacity by 240 MW. Without these steps, our country would have faced serious electricity shortages,” Japarov explained.
He also added that plans are in place to construct about one hundred new hydropower plants, modernize existing stations, and integrate solar and wind energy sources, which will create a reliable basis for the country's energy independence.
“Construction is underway for a thermal power plant with a capacity of 1,200 MW in Kara-Keche, as well as the Kambar-Ata-1 project. The construction of the Kambar-Ata HPP-1 with a capacity of 1,860 MW will become the largest energy project in the history of Kyrgyzstan. With the launch of this station, our country will not only be able to fully meet its internal needs but also become an exporter of electricity, supporting the energy stability of neighboring countries. This project symbolizes the power of the nation, economic independence, and the strategic future of Kyrgyzstan,” the president added.
Information about the Toktogul HPP
According to the State Enterprise "Electric Stations," the construction of the Toktogul HPP began in 1962, and it was commissioned in 1975. The station has four hydro units, each with its own serial number. According to the Ministry of Energy, the replacement of units is being carried out from 2022 to 2025:
- Hydro unit No. 4, which was first in line for replacement, was commissioned at the end of December 2022 (the official message from the Ministry of Energy is dated December 20, 2022).
- The new hydro unit No. 2, second in line for replacement, was fully installed and underwent commissioning work in early December 2023 (the message from "Electric Stations" was published on December 12, 2023).
- Hydro unit No. 1, which became third in line for replacement, was launched at the end of November 2024 (the official message from the Ministry of Energy about the launch was received on November 19, 2024).
- The new hydro unit No. 3, the last in line for replacement, will be replaced by mid-November 2025 (the official message from the Ministry of Energy is expected on November 12, 2025).
Information about the Kambar-Ata HPP-1
The dam of the Kambar-Ata HPP-1 will be located in the Toktogul district, approximately 9 km upstream from the Kambar-Ata HPP-2 and 75 km from the dam of the Toktogul HPP on the Naryn River. According to the latest data, the project cost is $3.5 billion, as confirmed by Energy Minister Talaybek Ibraev in January 2025 at a meeting of the parliamentary committee on international affairs.
According to the project's technical specifications, the main construction is planned to begin in 2027, with full commissioning expected by 2035.
In recent years, preparatory work has been carried out at the construction site of the HPP, including the construction of a road, bridge, substation, workers' town, tunnel, and power lines funded by the budget. The installed capacity of the Kambar-Ata HPP-1 will be 1,880 MW, and the average annual electricity generation will be approximately 6 billion kWh, which will ensure an increase in production of more than one-third from the current level. The height of the dam will be 260.8 meters, and the total volume of the reservoir will be 5.4 billion cubic meters.
Read also:
Kazue Miura will continue his career for another season
Kazuyoshi Miura, who is now 58 years old, has decided to continue his performances on the football...
Sadyr Japarov participated in the event ahead of the First Dialogue Summit "Central Asia + Japan" in Tokyo
President of Kyrgyzstan, Sadyr Japarov, arrived on December 19 at the state guesthouse...
Sadyr Japarov: There is no place for violence against women and children in our society
The President of the Kyrgyz Republic, speaking at the IV People's Kurultai, emphasized that...
Askhat Alagozov: Sadyr Japarov Does Not Distribute Money on Social Media
Citizens are urged to be vigilant Askhat Alagozov, the press secretary of the president, reported...
Sadyr Japarov arrived in Japan on a working visit
On December 18, the President of the Kyrgyz Republic, Sadyr Japarov, began his working visit to...
Murder of a Woman by Her Ex-Husband: The Police Showed the Last Minutes of the Deceased's Life
On December 24, the press service of the Main Internal Affairs Directorate of Bishkek presented a...
Sadyr Japarov launched the first solar power plant with a capacity of 100 megawatts in Kemin
During his speech, Zaparov emphasized the importance of transitioning to alternative energy...
What is known about the former traffic officer suspected of murdering his ex-wife?
On December 23, a tragic situation occurred in Bishkek related to a divorce process. In the...
Sadyr Japarov participated in the ceremony of announcing bilateral documents within the framework of the business forum of the Dialogue "Central Asia + Japan"
Today, December 20, during his official visit to Japan, the President of the Kyrgyz Republic,...
Sadyr Japarov spoke at the First Dialogue Summit "Central Asia – Japan" in Tokyo
At the First Central Asia – Japan Dialogue Summit taking place in Tokyo, the President of...
The total volume of money transfers to Kyrgyzstan in October 2025 amounted to $340.5 million
According to the National Bank, the inflow of funds from the CIS countries to Kyrgyzstan has...
Agreement on Financing the Construction of the Railway "China - Kyrgyzstan - Uzbekistan" Signed
As part of the signed agreement, $2.3 billion has been allocated for the creation of the railway...
Kyrgyzstan is Self-Sufficient in Six Types of Socially Significant Products
The total number of socially significant products is nine...
Kyrgyzstan Becomes the Main Exporter of Used Cars from South Korea
According to information provided by Yonhap, during the period in question, Kyrgyzstan imported...
Sadyr Japarov spoke at the meeting of the Supreme Eurasian Economic Council in St. Petersburg
In St. Petersburg, the President of Kyrgyzstan Sadyr Japarov participated in a meeting of the...
Kyrgyzstan Remains Among the Largest Importers of Cars from South Korea
As of November this year, the United States has become the leader in importing passenger cars from...
"Gazprom Plans to Significantly Increase Natural Gas Supplies to Kazakhstan, Kyrgyzstan, and Uzbekistan"
Uzbekistan is expected to see the largest growth in gas consumption, with a projected increase...
Kazakhstan's Freedom Bank to Establish a Subsidiary in Kyrgyzstan
The new structure will become part of Kyrgyzstan's banking sector, with 100% of the...
Adylbek Kasymaliev: Kyrgyzstan has entered the top 50 best tourist destinations in the world
The results of the study were published by the respected publication Financial Times...
Sadyr Japarov spoke at the first session of the deputies of the Jogorku Kenesh of the VIII convocation. What did the president talk about?
Today, December 17, the President of Kyrgyzstan Sadyr Japarov opened the first meeting of the...
Sadyr Japarov spoke at the IV People's Kurultai (text of the speech)
Today, December 25, the President of Kyrgyzstan, Sadyr Japarov, addressed the people, the deputies...