Currently, the school has not yet been put into operation, as it is in the final stages of construction. During the roof installation, the Issyk-Kul regional department of the State Architectural and Construction Control did not accept the facility. The contractor, LLC "Energy-Nur Stroy," had already received several warnings from the department.
As a result of the incident, the department issued a written warning to the contractor and demanded the restoration of the damaged facility. Currently, the roof of the school has already been restored; however, the company has been fined 200,000 soms. The issue of suspending the contractor's license will be discussed at the next commission meeting.
After the authorized bodies complete their inspection and provide a positive conclusion, the Issyk-Kul regional department of architectural and construction control will finally accept the facility for operation.