In the Batken region, 400 km of 220/110/35 kV power transmission lines will be repaired.

Анна Федорова Economy
VK X OK WhatsApp Telegram
In the Batken region, the repair of 400 kilometers of power transmission lines with a voltage of 220/110/35 kV is planned.

According to the Batken Electric Networks Enterprise, the work will be carried out in accordance with the plans of the Ministry of Energy aimed at updating and modernizing the power grid infrastructure. The branch of JSC "NESC" will begin repairs on the overhead power lines of the specified voltage.

According to the approved plan for 2026, it is expected:

— major repairs of 20 km of lines;

— scheduled maintenance repairs of 380 km of lines.

The repair work is organized in preparation for the autumn-winter season of 2026–2027 and will be carried out in stages from March to November. It will cover the territories of the Kadamjay, Leilek, and Batken districts.

In particular, in the Sulukta area, scheduled work has already begun on the repair of 110 kV lines "Khoja-Bakirgan–Arka" and "Arka–Morskaya" with a length of 7 km. During these activities, 190 outdated insulators will be replaced with new ones, the line fittings will be updated, and modern equipment that meets current technical standards will be installed.

Reference Information

In 2025, the high-voltage overhead network service of the Batken Electric Network Company replaced 7,200 outdated insulators, installing 7,513 glass insulators. During the work, scheduled repairs were carried out on 1,264.75 km of lines and major repairs on 134.6 km.

Contact Information for Electricity Supply Inquiries

Call Center: 105

Batken RET: 0221 33-36-02

Sulukta RES: 0772 46-04-01

Leilek RES: 0221 55-54-78

Kadamjay RES: 0221 55-54-68

Kyzyl-Kiy RES: 0773 94-07-07

VK X OK WhatsApp Telegram

Read also: