- Major repair of canals — 53 km
- Concrete pavement installation — 20.09 km
- Canal concreting — 12.4 km
- Mechanical cleaning of canals — 20.8 km
- Major repair of hydraulic structures — 22 units
- Repair of water measurement stations — 145 units
- Installation of water measurement sensors — 500 units
Additionally, the current repair plan includes the following works:
- Repair of canals — 170.5 km
- Mechanical cleaning of canals — 81 km
- Repair of water measurement stations — 516 units
- Repair of hydraulic structures — 579 units
- Pump station "Zhyltir" — 1 unit
Furthermore, Omuraliyev noted that 21 billion soms have been allocated for the preparation of intra-farm irrigation networks in the region for the 2026 growing season.
Within this funding, the following works on intra-farm irrigation networks will be carried out:
- Repair of canals — 61 km
- Mechanical cleaning of canals — 528 km
- Manual cleaning of canals — 740 km
- Repair of water measurement stations — 2 units
- Repair of hydraulic structures — 917 units