Results of 2025 in Energy: From Tariff Increases to Major Projects

Арестова Татьяна Exclusive
VK X OK WhatsApp Telegram
- Tazabek presents an analysis of key events that occurred in the energy sector of Kyrgyzstan in 2025.

Consumption, Generation, and Import of Electricity

According to information provided at a meeting of the Ministry of Energy, the following indicators were recorded in Kyrgyzstan during the first nine months of 2025:


Electricity generation reached 11.3 billion kWh, including:


To eliminate the deficit, 2.7 billion kWh of electricity was imported.

Changes in Tariff Policy and Restrictions

In 2025, electricity tariffs were increased. As of May 1, the following rates apply for consumers:


This period also saw the introduction of various measures to regulate consumption: restrictions in government institutions and the establishment of a power limit of 3 kW per household connection during peak hours.

Construction of Small Hydropower Plants

Illustrative image
In 2025, 5 small hydropower plants with a total capacity of 43.59 MW were commissioned, including:
DateNameCapacityLocation
June 2025Boz-Uchuk HPP5.5Issyk-Kul region, Ak-Suu district
August 29, 2025Koysuu HPP9.0Issyk-Kul region, Issyk-Kul district
August 29, 2025Aksy HPP4.8Jalal-Abad region, Aksy district
August 29, 2025Issyk-Ata-2 HPP4.0Chui region, Issyk-Ata district
October 27, 2025Karakul HPP18Jalal-Abad region, Toktogul district, city of Karakul
November 2025Kozho-Kayir HPP (Bazarbay-Ata-3)0.6Batken region, Kadamjai district
November 28, 2025Shamshy HPP1.7Chui region, Chui district

Additionally, in 2025, the construction of the following small hydropower plants began:
NameCapacityLocationCompany
Kurak-Tektir-2 HPP1Osh region, Nookat districtLLC "Kara-Oy Zharlygy"
Kainama HPP-24.4Jalal-Abad region, Toktogul districtLLC "Yrys Ordo"

Development of Renewable Energy Sources

The first solar power plant (SPP) with a capacity of 100 MW, located in the Kemin district, was commissioned in the field of renewable energy sources. The investments were made by LLC "Eternal Energy".

In 2025, the construction of the following facilities began:


Major Projects: Kambar-Ata HPP-1 and 2

A competition is underway for the update of the feasibility study (FS) for the construction of Kambar-Ata HPP-1, previously referred to as the project of the century. A contract with the contractor has been signed, and work has already begun. The type of dam for the HPP has been determined. An additional $13.6 million has been allocated to the previously allocated $5 million from the World Bank for the implementation of these activities, and $1.5 billion has been allocated for the main construction works of Kambar-Ata HPP-1 for three countries (Kyrgyzstan, Kazakhstan, Uzbekistan).

Completed works:

Construction of the access road to Kambar-Ata HPP-1 up to 318 km along the Bishkek-Osh highway:


Completion of the unfinished section of tunnel T-2 with an exit portal (126 m):


Construction of the 110 kV AC substation (18 km) and 110/6 kV structure of Kambar-Ata HPP-1:


Construction of new access roads from passage No. 2 to the construction site:


Construction of the Right Bank Bridge over the Naryn River to HPP-1:


Construction of a temporary settlement for workers:


Plans for 2025 for the Kambar-Ata HPP-1 project:


Temporary settlement for builders:


Kambar-Ata HPP-2

Work continues on the commissioning of the second hydro unit of Kambar-Ata HPP-2.

The project includes the following lots:


On June 16, 2025, an agreement was signed with the Dec-SM consortium (China-Korea) for Lot 1, which came into effect on August 8, 2025.

On August 19, 2025, an agreement was concluded with the Dec-SM consortium (China-Korea) for Lot 2.

On September 9, 2025, an agreement was signed with Sinohydro Bureau 16-Sinohydro Joint Venture (China) for Lot 3. Currently, work is underway to prepare for the entry into force of the contracts for Lots 2 and 3. By the end of October 2025, advance payments of 10% of the contract amount are planned. For Lot 1, work has begun on mobilizing contractors, and the construction of temporary offices and living quarters is underway. Preliminary studies and data collection on existing schemes for turbine model preparation are being conducted in parallel.

From October 28 to 31, 2025, a meeting with contractors from the three lots, representatives of the Eurasian Fund for Stabilization and Development (EFSD), and the project consultant is scheduled at the Kambar-Ata HPP-2 site to coordinate further steps for project implementation.

Modernization of Existing HPPs

Toktogul HPP: A large-scale modernization has been completed, resulting in an increase in the station's capacity from 1200 MW to 1440 MW (+240 MW). All four hydro units have been upgraded and now have a capacity of 360 MW each. The last unit was modernized from March to November 2025.

Uch-Korgon HPP: In 2024–2025, two of the four hydro units were replaced, increasing capacity by 18 MW. The upgrade of the remaining two units is planned for 2026.
VK X OK WhatsApp Telegram

Read also: