The Ministry of Construction issued a warning to the contractor for falling behind schedule on the construction of a kindergarten in Toktogul.

Сергей Гармаш Education
VK X OK WhatsApp Telegram
In accordance with the directive from the Minister of Construction, Architecture, and Housing and Communal Services Nurdana Oruntaeva, inspections at construction sites across the country are ongoing.

The press service of the Ministry of Construction reports that inspectors from the Jalal-Abad Regional Department of State Architectural and Construction Control conducted an inspection of construction work at a preschool educational institution designed for 140 places, located at: Abysheva Street 52 in the Toktogul district.

During the inspection, it was found that the soil compaction work has been completed, and the leveling of the construction site is currently underway.

According to the current work schedule, concrete work was supposed to start in January 2026. However, at this time, the contractor has not yet begun pouring concrete, indicating a significant delay from the planned timelines.

As a result of the inspection, reports on violations of the contract conditions and work schedule were drawn up. The contracting organization was issued an official warning requiring them to eliminate delays and expedite the construction work as soon as possible.

The contractor is the company "Kaanbak-Stroy," according to the Ministry of Construction.