- On March 2, 2026, Minister of Energy Talaybek Ibraev, as part of the execution of President Sadyr Japarov's directive, visited the Issyk-Kul region. The main goal of the trip was to assess the current state of energy facilities and major projects planned for 2026, the press service of the Ministry of Energy reported.

At the beginning of his visit, the minister met with employees of the branch of JSC "NESC" - the Issyk-Kul Electric Networks Enterprise, where important issues in the energy sector were discussed. Employees received answers to their inquiries, and the minister instructed to expedite the installation of "smart" meters and take measures to reduce electricity losses.

Additionally, a task was set to create the Kara-Sai Electric Networks subdivision to service the "Bedel" checkpoint, as well as the Oi-Tal subdivision at the Tyup RES for nearby settlements.

The minister also reviewed the project for the construction of a thermal power center in Karakol, which is planned to have a capacity of 120 MW with connection to the electrical networks via the 110/35/10 kV "Przhevalsk" substation. Upon completion of construction, the center will fully supply the city with the necessary electricity.

During the visit, the minister visited the racetrack in Baktyu-Dolonotu, where he discussed issues of reliable power supply and capacity enhancement in connection with the upcoming SCO summit and the III World Nomad Games.

At the Cholpon-Ata RES, the minister familiarized himself with the administrative building, which underwent major repairs. He listened to the employees' suggestions and promised to provide the subdivision with the necessary specialized equipment.

Additionally, within the framework of the trip, the modernization of the "Dolinka" substation was discussed. According to the project, the old transformers AT1-10 and AT2-16 MVA will be replaced with two new transformers of 40 MVA each, which will allow for the creation of a new substation with a total capacity of 80 MVA.

The minister also visited the "El-Nuru" energy workers' health resort to check the progress of construction works and readiness for the summer season. Currently, five two-story and five one-story cottages are being built on the territory of the health resort, with a total capacity of 50 places.

Furthermore, a complete modernization of the water supply system for the health resort is being carried out. The minister instructed to ensure the quality of work and complete construction by June 10, 2026.