The work is scheduled from March to November of this year.
The financing for the equipment upgrade is being carried out by JSC "KUET," while the actual implementation is handled by BPEE.
During the repairs, the technical condition of the transformers will be checked, worn components will be replaced, and necessary maintenance will be performed. "The installation of new transformers will improve the quality of electricity transmission, balance loads, and ensure stable power supply for consumers," the statement says.
It is planned to carry out work in the following districts:
- Eastern RES - 113 units under repair, 25 new;
- Western RES - 100 units under repair, 3 new;
- Northern RES - 85 units under repair, 10 new.
All of them will be fully covered by maintenance and repair work by the end of the year.