In Naryn Region, 21 transformers will be replaced and six additional units will be installed in 2026.

Ирэн Орлонская Exclusive
VK X OK WhatsApp Telegram
In the Naryn region, 21 transformers will be replaced in 2026 and six additional units will be installed

As reported by the Ministry of Energy, the plan for capital and current repairs also includes 2,015 transformers.

In the past year, 2025, the Naryn Electric Networks Enterprise replaced and installed 83 transformers, including: • 61 transformers with a voltage of 10/0.4 kV were replaced; • 22 transformers with a voltage of 10/0.4 kV were additionally installed.

As a result of these activities, the total electrical capacity increased by 39,217 kVA compared to the previous year. In addition, 121 transformers were transferred to the balance of the Naryn Electric Networks Enterprise. All ongoing work is aimed at ensuring quality and stable electricity supply for the population.
VK X OK WhatsApp Telegram

Read also: