At what stage is the construction of the new terminal complex of Osh Airport?

Марина Онегина Society
VK X OK WhatsApp Telegram
During his working trip to Osh, the Minister of Construction, Architecture, and Housing and Communal Services, Nurdana Oruntaev, checked on the progress of the construction of the new terminal complex at the international airport "Osh." This information was provided by the ministry's press service.

According to their data, the area of the new terminal is 26,000 square meters and includes six blocks. Construction work started on April 25, 2025.


Currently, 95 percent of the monolithic work has been completed. The installation of engineering systems in the basement, including power supply, ventilation, sewage, water supply, and fire-fighting water supply, has reached 80 percent completion. Work on the first floor has been temporarily suspended due to the need to make changes to the design and estimate documentation.

“The minister emphasized the importance of quality and timely completion of construction, as well as the need for prompt changes to the design and estimate documentation and increasing the pace of work by raising the number of workers,” the press service reported.

Currently, about 120 workers are employed at the construction site, and there are plans to double this number.