The Cabinet approved agreements with the EBRD for the 500 kV Kemin–Balykchy power line project

Елена Краснова Exclusive
VK X OK WhatsApp Telegram
The Cabinet of Ministers has made a decision to implement projects related to credit and grant agreements with the European Bank for Reconstruction and Development. These agreements are aimed at constructing a 500 kV overhead power line connecting the "Kemin" substation and the new "Balykchy" substation. The order on this matter was signed on December 31, 2025.

According to this document, the Minister of Finance of the Kyrgyz Republic has been granted the authority to sign agreements, including the ability to make amendments that do not affect the fundamental aspects.

Financial parameters of the project



The project aims to improve the reliability of the energy system in the northeastern part of Kyrgyzstan, increase the capacity of the main power grids, and ensure stable electricity supply. Its implementation is expected to create conditions for further development of energy infrastructure and integration of regional energy networks.

The completion of all project works is scheduled for the end of 2031.