Currently, the following work has been completed as part of the project:
- Site planning - 80%;
- Installation of fencing - 95%;
- Delivery of supporting structures for the first phase - 50%;
- Piling for supporting structures of the first phase - 6%;
- Construction of sediment control structures, including a drainage channel and drainage ponds - 50%;
- Preparation of pits for 220 kV power line supports - 40%;
- Assembly of supports is ongoing.
It is expected that the 100 MW solar power plant will be commissioned on August 31, 2026.
Additionally, Ibraev also inspected the construction of the solar power plant being carried out by the company "RECA". He met with the project director Fam Minh Bag and the site manager Nguyen Minh Tuan, who provided information on the progress of the project. According to them, 10% of the construction work on the 17 MW solar power plant has been completed so far.
The construction of temporary housing for workers has now been completed, the foundation for the substation has been laid, and 50% of the 110 kV power line has been installed. The completion of the first phase of the 175 MW project is scheduled for the first half of 2026.
The Minister of Energy emphasized to the company's management the need to strengthen control over the quality and pace of work, highlighting the importance of adhering to construction deadlines.