At the Kambaratin HPP-2, the installation of structures for the new hydro unit has begun

Анна Федорова Economy
VK X OK WhatsApp Telegram
Construction of structures for the new hydro unit has begun at the Kambarata HPP-2
Photo by the Ministry of Energy. Kambarata HPP-2
In Kyrgyzstan, the installation of structures for the second hydro unit at the Kambarata HPP-2 has begun. This project aims to increase the country's energy capacity and strengthen the reliability of its energy system, as reported in a press release from the Ministry of Energy.

Funding and Contractors


The project is financed with the support of the Eurasian Stabilization and Development Fund. To ensure the quality of the work, the ministry has signed a contract with the international company Fichtner GmbH & Co. KG, which will provide technical support and oversee engineering works.

Photo by the Ministry of Energy. Site for the second hydro unit at Kambarata HPP-2
The scope of work is divided into three lots, allowing for the involvement of specialized experts with international experience:

Current Work and Achievements


Currently, a significant amount of preparatory and construction work has been completed:


The project is progressing on schedule. The commissioning of the new hydro unit will increase electricity production and create a solid foundation for the further development of Kyrgyzstan's energy sector, enhancing its resilience to peak loads.