Construction of the Orto-Tokoy Hydroelectric Power Station is entering the final stage
According to the Ministry of Energy, construction work is proceeding according to the established schedule. The diversion tunnel, 950 meters long, has been successfully completed and is currently being reinforced with concrete. Ground reinforcement at the tunnel branching point has also been completed, and the walls of the chamber have already been erected. The installation of the tunnel interchange is planned soon, where metal structures have already been installed in two of the three exits.
The construction of the hydroelectric power plant itself is nearing completion, and the readiness of the facility is currently at 90%. All three hydroturbines and disc gates have been installed, and the roof frame has been assembled. Roofing work is actively underway, and some other construction processes are being completed.
The work is being carried out by JSC "Chakan HPP". The expected capacity of the Orto-Tokoy HPP will be 21 megawatts, and the completion of construction is scheduled for the first half of 2026.
It is worth noting that the project for the construction of the Orto-Tokoy HPP received government approval in July 2021. The contract for the implementation of the project was signed on March 24, 2023, and actual construction work began in June 2024.
It is expected that the capacity of the Orto-Tokoy HPP will provide electricity to 15,000 to 18,000 households annually, depending on the level of consumption.
Read also:
Construction of the Orto-Tokoy Hydroelectric Power Plant is 80% complete, - OJSC "Chakan HPP"
According to information from OJSC "Chakan HPP," construction work at the Orto-Tokoy HPP...
Ministry of Energy: Construction of the Orto-Tokoy Hydroelectric Power Station is nearing completion
According to the information from the press service of the Ministry of Energy, OJSC "Chakan...
Construction of the Orto-Tokoy Hydroelectric Power Station is planned to be completed in the first half of 2026.
According to information provided by the Ministry of Energy of Kyrgyzstan, OJSC "Chakan...
The Minister of Construction inspected the construction of wastewater treatment facilities in Cholpon-Ata
On January 7, the Minister of Construction, Architecture, and Housing and Communal Services Nurdin...
In the Oktobrskiy District of Bishkek, 13 schools and 17 kindergartens will be built
In response to citizens' inquiries regarding social infrastructure in the village of Orto-Sai...
In the village of Zhany-Talap, a new school building has been constructed in the Aksy district.
In the village of Zhany-Talap in the Aksy district, located in the Jalal-Abad region, the...
In the city of Kainy, the construction of a new administrative building is underway.
During the visit, the minister met with the staff of the department and announced that the new...
A new building of the Ministry of Justice has been constructed in Manas
A new building for the Ministry of Justice has been completed in Manas. According to the Ministry...
Ministry of Construction: Wastewater Treatment Facilities are Actively Being Built in Cholpon-Ata
The construction began in July 2025 and is being carried out by the companies "China...
Minister Oruntaev checked the progress of the construction of the IT town "Osh-City": the commissioning of the first blocks is scheduled for the summer of 2026.
- The Minister of Construction, Architecture, and Housing and Communal Services, Nurdin Oruntaev,...
Kyrgyzstan will produce system units for personal computers
Kyrgyzstan will begin the production of system units for personal computers, as announced by the...
2,500 spaces are not enough. Where will the residents of the "Muras" complex from GIK park?
Today, January 12, at the event dedicated to the handing over of keys for the second phase of the...
The Eastern Bypass Road in Bishkek is planned to be completed in one to two years.
As part of the discussion on the general plan for the capital Bishkek, Vice Mayor Azamat Kadyrov...
Tashiev criticized the timelines and quality of the construction of the "Balykchy–Barskoon–Karakol" highway and took the work under personal control
On December 27, 2025, during his working trip to the Issyk-Kul region, Colonel General Kamchybek...
In Naryn Region, electricity consumption limits have been increased
The increase in electricity consumption limits in the Naryn region has become possible thanks to a...
Naryn PES Increases Power of Electric Networks by 5 kW for 61.2 Thousand Subscribers
- The press service of the Naryn Electric Power Station informs that the total number of clients...
Kyrgyzstan Plans to Electrify Over 200 km of the Turksib - Balikchy Railway
The project will be implemented with the involvement of investments....
Construction of wastewater treatment facilities in Cholpon-Ata inspected by Nurdin Oruntaev
The head of the Ministry of Construction, Architecture, and Housing and Communal Services, Nurdana...
The Housing and Communal Services Committee for the Fuel and Energy Complex approved the project for the construction of an overhead power line between the "Kemin" substation and the new "Balikchy" substation.
- At an extraordinary meeting held on December 26, the Committee on Industrial Policy, Transport,...
In the village of Otuz-Adyr in the Kara-Suu district, the construction of a new kindergarten has been completed.
In the Kara-Suu district of the Osh region, in the village of Otuz-Adyr, the construction of a new...
Tender announced for the design of a school building in the village of Zhangarach, Sokuluk District
A tender has been announced at the Chui Regional Department of Capital Construction of the...
"In 10 years, the number of schoolchildren has increased by half a million, - president on the shortage of schools"
President Sadyr Japarov drew attention to one of the most pressing issues raised at the IV...
Construction of the first oil refinery in Mongolia is 50 percent complete
In Mongolia, the project for the first large oil refinery is actively being implemented, located...
In the Ala-Archa Natural Park, a cable car is being tested
In the Ala-Archa Natural Park, test works are underway on the under-construction cable car. Videos...
Results of 2025. Launched Large-Scale Projects
- In 2025, Kyrgyzstan took an important step forward by launching several major infrastructure...
In the village of Vinogradnoye, a new livestock market is being built
In the village of Vinogradnoye, located in the Chuy region, the implementation of the project for...
President on the construction of the BSR and BDR: All facilities can be completed in 4-5 years
- At the IV People's Kurultai, held on December 26, President Sadyr Japarov commented on the...
Bishkek Master Plan. The capital doesn't need a metro, and building a monorail along the rivers is pointless, - architect
At an extraordinary meeting of the committee of the Jogorku Kenesh held on December 26, the chief...
"Paying for the samsas we didn't eat." The President on the Upper Naryn Cascade of Hydroelectric Power Plants
At the IV People's Kurultai, President Sadyr Japarov responded to a delegate's proposal...
The road to Zardala was opened for traffic for 888.9 million soms — the president participated
In the Batken region, the construction of a road has been completed, costing 888.9 million soms....
In Uzbekistan, restrictions have been imposed on the operation of methane filling stations
Starting January 8, methane filling stations in Uzbekistan will begin operating on a limited...
In Osh Region, 18 facilities were opened — details announced
In the Osh region, the opening of three new production enterprises and 15 social facilities took...
Sadyr Japarov: In 2025, 4,600 families became homeowners
Today, while speaking at the People's Kurultai, the President of the Kyrgyz Republic, Sadyr...
A free hotel for pilgrims from Kyrgyzstan has begun construction in Mecca
Construction has begun on a hotel in Mecca that will provide free accommodation for citizens of...
The Ministry of Transport has completed the construction of a road to the remote village of Zardaly
In the Batken region, the construction of a road connecting Sary-Talaa, Kyzyl-Tash, and Zardaly has...
Holders of "Tulpar" cards will be able to pay for transportation in Tashkent
The project for the implementation of cashless payments in public transport in Bishkek, called...
In 4 years, 28 new hydropower plants with a total capacity of over 400 MW have been built, - President Japarov
Today, December 25, President Sadyr Japarov announced at the IV People's Kurultai significant...
Tashiev ordered the arrest of the contractor for the Balykchy–Karakol road
On December 27, 2025, during a working visit to the Issyk-Kul region, Kamchybek Tashiev, Deputy...
Bishkek CHPP switched to enhanced operating mode
Photo courtesy of the mayor's office In connection with the upcoming New Year celebrations,...
The Ministry of Construction is building a district administration building in the Panfilovsky District using its own funds.
The facility will be put into operation soon According to the press service, a new administrative...
In Bishkek, a section of Budenny Street is temporarily closed.
In Bishkek, work has begun on the creation of sewage networks on Kulikovskaya Street, Slavyanskaya...
In the Jayil District, the livestock market does not meet standards: Plans to create a temporary site until the new market is built
As part of his working trip to the Jayyl district, the presidential envoy in the Chui region,...
Construction of two schools has begun in the southern zone of Bishkek, - vice-mayor
In the southern part of Bishkek, the construction of two educational institutions has begun,...
Ulaanbaatar to Build and Upgrade 85.8 km of Roads in 2026
The planned works will cover a total of 85.8 kilometers of road infrastructure. The project also...
Fountain in Oak Park – Bishkek City Hall commented on its demolition
Part of the historical structure has been transferred to "Tazalyk" for safekeeping...
The Unified Technical Regulation System of the EAEU Ensured Deliveries of Over 85% of Products According to Unified Requirements
- In an interview provided by the Deputy Director of the Department of Technical Regulation and...
The President was shown a fish feed production plant in the Chui region
According to the information provided at the meeting, 5 million US dollars were allocated for the...