Over 62 million soms from the republican budget were allocated for the implementation of this large-scale reconstruction. During the work, more than 15 kilometers of water supply networks were laid, and two reinforced concrete reservoirs were built, each with a capacity of 300 cubic meters of water.
To enhance sanitary safety in the village, a special building was constructed, housing a modern bactericidal unit for water purification. The project also includes safety measures: 12 fire hydrants and 600 individual water meters have been installed in the village to monitor water consumption.
With the launch of the new infrastructure, 600 households now have access to quality and safe drinking water. Experts from the relevant department note that the commissioning of the system will not only significantly improve the living conditions of local residents but also create a foundation for further economic growth in the region.