The Antimonopoly Service approved new rates for the examination of design and estimate documentation

Сергей Мацера Economy
VK X OK WhatsApp Telegram
- On December 29, 2025, Order No. 108 of the Antimonopoly Regulation Service under the Ministry of Economy and Commerce was signed, concerning the cost of expertise for project and estimate documentation for individuals and legal entities.
This document covers the services provided by the State Expertise Department, which operates under the auspices of the Ministry of Construction, Architecture, and Housing and Communal Services.

The new price list was approved based on materials submitted by the department and in accordance with the current regulations of the Cabinet of Ministers.

According to the order, the previously effective document dated May 16, 2025, No. 36, which defined the tariffs for paid services of the department, is no longer in effect.

Main provisions of the order:


The new rates come into effect upon their approval.

Defined tariffs for expertise:



Tariffs for expertise of individual projects (soms)
No.Object nameUnit of measurementCost (soms) per unit
1Residential buildingssq.m68.0
2Individual residential housessq.m38.0
3Public buildings (institutions, educational establishments, hotels, dormitories)sq.m61.0
4Healthcare facilitiessq.m75.0
5Shopping centers, stores, catering establishments, bathssq.m69.0
6Sports facilities, indoor pools, and sports groundssq.m92.0
7Industrial buildings, refrigeration and repair workshops, gas stations, warehouses for hazardous materials, and boiler housessq.m82.0
8Garages, parking lots, underground parking, auxiliary premisessq.m42.0
9Canopies, outdoor pools, terracessq.m31.0


Tariffs for expertise of reusable and standard projects (soms)
No.Object nameTotal area unitCost (soms) per unit
1Residential buildingssq.m26.0
2Individual residential housessq.m15.0
3Public buildings (institutions, educational establishments, hotels, dormitories)sq.m39.0
4Healthcare facilitiessq.m31.0
5Shopping centers, stores, catering establishments, bathssq.m29.0
6Sports facilities, indoor pools, and sports groundssq.m38.0
7Industrial buildings, repair workshops, gas stations, warehouses for hazardous materials, and boiler housessq.m34.0
8Garages, parking lots, underground parking, auxiliary premisessq.m18.0
9Canopies, outdoor pools, terracessq.m12.0


Cost of expertise for reconstruction projects (soms)
No.Object nameTotal area unitCost (soms) per unit
1Residential buildingssq.m41.0
2Individual residential housessq.m22.0
3Public buildings (institutions, educational establishments, hotels, dormitories)sq.m33.0
4Healthcare facilitiessq.m45.0
5Shopping centers, stores, catering establishments, bathssq.m42.0
6Sports facilities, indoor pools, and sports groundssq.m58.0
7Industrial buildings, repair workshops, gas stations, warehouses for hazardous materials, and boiler housessq.m53.0
8Garages, parking lots, underground parking, auxiliary premisessq.m26.0
9Canopies, outdoor pools, terracessq.m18.0


Tariffs for expertise of various projects (soms)
No.Object nameTotal area unitCost (soms) per unit
1Roads (reconstruction, new construction)linear m.14.0
Sidewalks, bike pathslinear m.10.0
2Bridges, overpasses, viaducts, underground passages, galleries, culvertssq.m272.0
3Tunnels (linear m.)linear m.272.0
4Runway surfaces (reconstruction, new construction)sq.m3.0
5Open parking lots and drivewayssq.m2.0
6Heat network, steam pipelinelinear m.53.0
7Engineering infrastructure (substations, water intakes, treatment facilities, etc.)sq.m60.0
8Dams, protective structures, retaining wallssq.m38.0
8.1Shore protection and debris control dams (budget)sq.m11.0
9Power lines up to 10 kV and communication cable lines up to 10 kVlinear m.14.0
Power lines over 10 kVlinear m.20.0
10Other objects (billboards, monuments, etc.)sq.m31.0
11Automation (fire alarm systems and gas supply systems)sq.m3.0
12Estimates (item)item60.0
13Towers, masts, supports (by height)linear m.820.0
14Water supply networkslinear m.11.0
Drilling wellslinear m.195.0
15Gas pipelinelinear m.19.0
16Sewage networks, irrigation, and drainage channelslinear m.24.0


Notes:

1) The areas of built-in objects and premises are calculated separately depending on their purpose;

2) For documents with changes after expertise, the cost is determined based on the area where changes were made;

3) When designing and constructing simultaneously, payment for expertise is made at the first stage;

4) If projects have similar characteristics, the cost calculation is made only for one building;

5) Project documents with changes to load-bearing structures are considered reconstruction;

6) For re-expertise of documents that previously received a negative conclusion, the client pays 20% of the cost of the previous expertise;

7) For objects financed from the budget, the cost of expertise is determined by special items in the table;

8) The area of dams and walls is calculated using special formulas;

9) Mandatory taxes are not included in the cost of services.