This project is considered a "project of the century," and currently, the construction of a shift camp is underway, along with the installation of power lines, as well as the construction of a bridge and roads.












Currently, the following works have been completed:
- The concrete road from 318 km of the Bishkek - Osh road to cut No. 2, which is 8.6 km long, has been fully completed and is in the acceptance stage;
- The construction of a 4.7 km long road from cut No. 2 to the Kambar-Ata HPP-1 site is almost complete, with about 4 km done (almost 95%);
- All work on the transport tunnel TT-2 (126 m) has been completed, and the facility is undergoing acceptance;
- 11.5 km of 110 kV overhead power line has been laid, and a 110/6 kV substation has been built, where the main work is 90% complete;
- The construction of a shift camp for 100 people (including an administrative building, dormitory, and cafeteria) is 60-70% complete;
- The concreting of four supports of the bridge over the Naryn River has been completed, and the installation of metal structures is underway, with the total length of the bridge exceeding 180 m and its readiness at 50-60%;
- The concrete road in the transport tunnel TT-2 (1,387 m) has been fully completed, and internal structural work is ongoing (overall readiness 55-60%).